Process ControlUpdated 3 September 2026

OEE

Overall Equipment Effectiveness: availability multiplied by performance multiplied by quality, giving the share of planned time that produced good output at full speed.

OEE multiplies three ratios: availability (was the equipment running), performance (was it running at rate), and quality (was the output good first time). The result is the share of planned production time that produced sellable output at the intended speed.

They multiply rather than average, which is why the figure looks severe — 90% on each gives 73% overall. That severity is the useful part. Three tolerable losses compound into an intolerable one, and the arithmetic shows it in a way three separate percentages never do.

O número isolado praticamente não tem significado por si só. O que realmente traz valor é a divisão: perdas dominadas pela disponibilidade na manutenção e nas mundaças de formato, perdas de desempenho nas pequenas paragens e no funcionamento lento, perdas de qualidade na capacidade do processo. Três projetos diferentes, e o rácio diz-lhe qual deles tem em mãos.

It degrades badly when used as a target. Planned downtime gets inflated, equipment gets run past what the process will hold, rework gets counted as good — all of which raise the number and none of which improve anything. It is a diagnostic. Treated as a KPI it becomes fiction, and comparing it between machines or sites was never valid in the first place.